Experiences Categories: New Construction
Lewistown Press Box
UIUC Life Home – Research and Laboratory Facility
Urbana Post Office
Richland Community College
Danville Area Community College
Yankee Ridge Elementary School
A total of 67,000 SF between the additions and renovations were completed in three phases, two of which were completed in 8 weeks each during the 2017 and 2018 summers. The addition work (a new gymnasium, fine arts wing, 10 classrooms, 4 restrooms and a new cafeteria and kitchen), took place while the Owner used the school resulting in continuous, intense coordination and communication. This $9.4 million project started in June of 2017 and was completed August 2018.
Cunningham Children’s Home
A new 50,240 sf, single-story building constructed, along with a new main entrance and various site improvements