Lutheran High School

Construction of a 19,120 sf addition with classrooms, administrative offices, learning commons, chapel, and restrooms.

Corpus Christi

Six classroom addition to the existing school, including restrooms, storage and mechanical rooms.

Yankee Ridge Elementary School

A total of 67,000 SF between the additions and renovations were completed in three phases, two of which were completed in 8 weeks each during the 2017 and 2018 summers. The addition work (a new gymnasium, fine arts wing, 10 classrooms, 4 restrooms and a new cafeteria and kitchen), took place while the Owner used the school resulting in continuous, intense coordination and communication. This $9.4 million project started in June of 2017 and was completed August 2018.

Good Shepherd Lutheran

Construction of a 6,450+ sf classroom additiona and miscellaneous renovations to the existing building